Purva Northern Lights Latest News
Purva Northern Lights, is a RERA-approved residential township in KIADB Aerospace Park, Bagalur Road, North Bangalore. The project launched on 25 March 2026. Construction began on 15 April 2026, with possession scheduled for 31 December 2029.
Purva Northern Lights is now officially launched by Puravankara Limited. The EOI phase ran through February 2026. The official launch happened on 25 March 2026, and site work is now active. This page tracks all key updates as the project moves forward.
Here is what buyers and investors need to know right now about Purva Northern Lights Hardware Park.
Expression of Interest (EOI) Started
The EOI process for Purva Northern Lights Bangalore opened in February 2026. It gave early buyers priority access to apartment selection before the official launch. The project launched on 25 March 2026. If you registered during EOI, you had first access to unit choices across 1 BHK, 2 BHK, 3 BHK, and 4 BHK configurations.
RERA Approved: 12 March 2026
Purva Northern Lights received RERA approval on 12 March 2026. The registration number is PRM/KA/RERA/1251/309/PR/120326/008523.
This matters because RERA registration locks the developer into a legally binding construction schedule. Any delay beyond the committed date of 31 December 2029 makes Puravankara liable under Karnataka RERA rules. You can verify the registration, construction milestones, and promoter details directly on rera.karnataka.gov.in.
Purva Northern Lights covers 24.55 acres in KIADB Aerospace Park, Bagalur Road, North Bangalore. The township is designed so 80% of the land stays open and green. Only 20% is built up, which is unusual for a project at this scale and price point.
Purva Northern Lights Phase 1 has 1,225 apartments across 3 towers. The full project covers 2,973 units across 8 towers on a 24.55-acre site. You can choose from 4 unit types:
- 1 BHK: Carpet area 408 sq.ft
- 2 BHK: Carpet area 670 – 768 sq.ft
- 3 BHK: Carpet area 1,003 – 1,077 sq.ft
- 4 BHK: Carpet area 2,235 – 2,332 sq.ft
For current pricing, visit the Purva Northern Lights Price Page.
This makes Purva Northern Lights a strong choice for families looking for luxury, comfort, and well-planned living spaces in North Bangalore.
Construction Timeline
- Pre-Launch Date: 15 March 2026
- Launch Date: 25 March 2026
- Construction Start Date: 15 April 2026
- Construction Duration: 3 Years 8 Months
- Expected Completion: 31 December 2029
- Possession Date: 31 December 2029 (as per RERA registration)
The project launched on 25 March 2026 and construction begins on 15 April 2026. All timelines are RERA-registered and legally binding.
RERA-Verified Construction Milestones
- Earthwork and site leveling: 15 April 2026 – September 2026
- Foundation and footing work: August 2026 – March 2027
- Plinth level completion: November 2026 – November 2027
- RCC superstructure framing: February 2027 – November 2027
- Masonry and plastering: February 2027 – December 2029
- Doors, windows, and joinery: July 2027 – September 2029
- Flooring and tiling: November 2027 – October 2029
- Painting: May 2028 – December 2029
- Elevation and landscaping: December 2028 – December 2029
You can verify this schedule directly on rera.karnataka.gov.in.
The project is now in active construction. Earthwork and site levelling began on 15 April 2026 and run through September 2026.
Why Location Matters
Purva Northern Lights is located in North Bangalore, near KIADB Aerospace Park and Hardware Park. It makes the project ideal for families and professionals. The area offers:
- Easy access to major IT hubs and tech parks
- Proximity to airports, schools, colleges, and hospitals
- Connectivity via NH 44, STRR, and Namma Metro Blue Line Phase 2B
- Doddajala Metro Station is roughly 2 km from the site
This smart location saves travel time and makes daily life easier for families.
Amenities and Lifestyle Features
Purva Northern Lights is not just an apartment project; it’s a complete integrated township. Key features are given below.
- Wide green open spaces for kids and families
- Dual clubhouse spanning 1 lakh sq.ft with 80+ amenities
- Swimming pool and gym for fitness lovers
- Kids' play area and dedicated social spaces
- Safe, vehicle-free central areas for peace of mind
The township design ensures that residents have everything inside one place, from recreation to daily needs.
Purva Northern Lights sits in one of North Bangalore's fastest-growing corridors. The KIADB Aerospace Park zone has seen strong infrastructure investment since 2022, with NH 44, STRR, and the Namma Metro Blue Line Phase 2B all converging nearby. Doddajala Metro Station is roughly 2 km from the site.
Puravankara Limited has delivered over 80 projects across India since 1975. The Phase 1 contractor for this project is Kalpataru Projects International. The architect is Kembhavi Architecture, a Bengaluru-based firm registered with the Council of Architecture. Both are named in the RERA filing and can be verified on rera.karnataka.gov.in.
Purva Northern Lights is one of the most active new launches in North Bangalore right now. Unit selection is open across 1, 2, 3, and 4 BHK configurations. If you want to lock in your preferred floor or tower, this is the right time to act.
Phase 1 of Purva Northern Lights carries a declared project cost of ₹859 crore in the RERA filing. That figure covers 1,225 apartments across 3 towers on 9.5 acres, with possession committed to 31 December 2029. If you want a legally secured timeline and a builder with a national track record, this project is worth evaluating now while unit selection is still open.