Purva Northern Lights construction is now active, with Phase 1 earthwork underway since April 2026. Puravankara Limited is building this RERA-approved township at KIADB Aerospace Park,
Bagalur Road, North Bangalore, Karnataka 562149. Kempegowda International Airport is about 8 km away.
Site work is active and on schedule per the RERA registration. Phase 1 earthwork and site levelling started on 15 April 2026. This stage runs through September 2026.
Latest News Snapshot of Purva Northern Lights – July 2026
- Current sales update: Puravankara Limited posted Q1 FY27 pre-sales of Rs 1,439 crore, up 28% year-on-year.
- Collections and pricing: Customer collections rose 40% to Rs 1,199 crore. Average price realisation improved 18% to Rs 10,589 per sq ft.
- Delivery track record: The company handed over 745 homes across 0.94 million sq ft this quarter.
- Zentech deal: Puravankara signed a deal with ICICI Prudential AMC to sell its Purva Zentech commercial property. Enterprise value stands at Rs 625.94 crore.
- Land pipeline near this project: Puravankara added an 11.23-acre parcel in Doddagubbi (GDV Rs 1,100 crore) and a 9.73-acre parcel in Sanna Ammanikere (GDV Rs 800 crore).
- FY26 track record: Highest-ever annual sales of Rs 7,407 crore, up 55%. Q4 FY26 PAT was Rs 111 crore, up 226%.
July 2026 Site Status – What's Happening Now?
As of July 2026, Purva Northern Lights is in active earthwork and site levelling. This stage runs through September 2026. The next milestone is foundation and footing work, starting August 2026. Buyers can verify unit sizes, current pricing and tower-wise availability before booking.
The project has moved past the EOI and pre-launch stage. Site updates next will cover foundation work, plinth completion, and RCC superstructure framing across all 8 towers.
Is Purva Northern Lights open for booking?
Yes, bookings are open across all four configurations, from 1 BHK to 4 BHK. The EOI phase ran through February 2026, giving early buyers first access to unit selection. The project launched officially on 15 March 2026, and construction started on 15 April 2026.
When Was Purva Northern Lights RERA Approved?
Purva Northern Lights received RERA approval on 12 March 2026. The registration number is PRM/KA/RERA/1251/309/PR/120326/008523.
This matters because RERA locks the developer into a binding construction schedule. Any delay beyond the committed date of 31 December 2029 makes Puravankara liable under Karnataka RERA rules. You can verify the registration and milestones directly on rera.karnataka.gov.in.
The project covers 24.59 acres in KIADB Aerospace Park, Bagalur Road, North Bangalore. It is designed so 77% of the land stays open and green. Only 23% is built up, which is unusual for a project at this scale and price point.
Phase 1 has 1,225 apartments across 3 towers. The full township covers 2,973 units across 8 towers on the 24.59-acre site. You can choose from 4 unit types:
- 1 BHK: Carpet area 408 sq.ft
- 2 BHK: Carpet area 670 – 768 sq.ft
- 3 BHK: Carpet area 1,003 – 1,077 sq.ft
- 4 BHK: Carpet area 2,235 – 2,332 sq.ft
For current pricing, visit the Purva Northern Lights Price Page.
The 1 BHK at 408 sq. ft makes this project accessible to first-time buyers and investors. The 4 BHK at 2,235 sq. ft suits larger families looking for premium space in North Bangalore. All carpet areas are RERA-verified.
Construction Timeline
- Pre-Launch Date: 15 March 2026
- Launch Date: 15 March 2026
- Construction Start Date: 15 April 2026
- Construction Duration: 3 Years 8 Months
- Expected Completion: 31 December 2029
- Possession Date: 31 December 2029 (as per RERA registration)
It launched on 15 March 2026, with construction starting 15 April 2026. All timelines are RERA-registered and binding.
RERA-Verified Construction Milestones
| Construction Stage |
Start Date |
End Date |
| Earthwork and site leveling |
April 2026 |
September 2026 |
| Foundation and footing work |
August 2026 |
March 2027 |
| Plinth level completion |
November 2026 |
November 2027 |
| RCC superstructure framing |
February 2027 |
November 2027 |
| Masonry and plastering |
February 2027 |
December 2029 |
| Doors, windows, and joinery |
July 2027 |
September 2029 |
| Flooring and tiling |
November 2027 |
October 2029 |
| Painting |
May 2028 |
December 2029 |
| Elevation and landscaping |
December 2028 |
December 2029 |
You can verify this schedule directly on rera.karnataka.gov.in.
Active construction is underway. Earthwork and site levelling began 15 April 2026, running through September 2026.
What Are the Location Advantages in North Bangalore?
The project sits in North Bangalore, near KIADB Aerospace Park and Hardware Park. This makes it ideal for families and professionals. The area offers:
- Easy access to major IT hubs and tech parks
- Proximity to airports, schools, colleges, and hospitals
- Connectivity via NH 44, STRR, and Namma Metro Blue Line Phase 2B
- Doddajala Metro Station is roughly 2 km from the site
This smart location saves travel time and makes daily life easier for families.
Amenities and Lifestyle Features
This is not just an apartment project; it's a complete integrated township. Key features are given below.
- Wide green open spaces for kids and families
- Dual clubhouse spanning 1 lakh sq.ft with 80+ amenities
- Swimming pool and gym for fitness lovers
- Kids' play area and dedicated social spaces
- Safe, vehicle-free central areas for peace of mind
The township design ensures that residents have everything inside one place, from recreation to daily needs.
The project sits in one of North Bangalore's fastest-growing corridors. The KIADB Aerospace Park zone has seen strong investment since 2022, with NH 44, STRR, and Namma Metro Blue Line Phase 2B converging nearby.
Puravankara Limited has delivered over 80 projects across India since 1975. The Phase 1 contractor for this project is Kalpataru Projects International. The architect is Kembhavi Architecture, a Bengaluru-based firm registered with the Council of Architecture. Both are named in the RERA filing and can be verified on rera.karnataka.gov.in.
This is one of the most active new launches in North Bangalore right now. Unit selection is open across all four configurations. If you want a specific floor or tower, this is the right time to act.
Phase 1 carries a declared project cost of ₹859 crore in the RERA filing. That figure covers 1,225 apartments across 3 towers on 9.5 acres. Possession is committed to 31 December 2029. This project pairs a legally secured timeline with a builder that has a national track record. It's worth evaluating now, while unit selection is still open.