The Bengaluru Suburban Rail Project (BSRP) is among the most awaited infrastructure projects in Karnataka. As of 2026, the project has entered a crucial construction phase, especially on the Sampige Line (Corridor 1).
This corridor is planned to offer a fast and affordable rail connection between the city centre and KIA. It is expected to reduce the city’s dependence on road travel and airport taxis.
Latest Construction Progress in 2026
By early 2026, K-RIDE (Rail Infrastructure Development Company) had accelerated work on the Airport Corridor after multiple administrative delays. Although the Mallige and Kanaka lines were handled first, attention has now moved to the Sampige Line to address increasing travel needs in North Bangalore.
Tendering and Awarding:
Most civil construction contracts for the Sampige Line have been awarded to leading infrastructure companies.
Land Acquisition:
More than 90% of the land needed for the airport corridor has been acquired. This includes parcels from private landowners and Indian Railways.
Station Foundations:
Foundation piling and groundwork have begun at major stations such as Yelahanka and Devanahalli.
Utility Shifting:
Key electrical lines and water pipelines along the route have been relocated to avoid construction obstacles later.
Key Stations on the Airport Route
The Sampige Line covers nearly 41 Km and includes 15 well-planned stations, and these stations connect major urban zones with the northern outskirts of the city.
KSR Bangalore (Majestic):
The main point that starts offers a smooth transit facility to metro lines and long-distance rail services.
Hebbal:
A major interchange station serving the people from the northern part and the ORR corridor.
Yelahanka:
An important junction catering to the large residential population of Yelahanka New Town.
Bettahalasuru & Doddajala:
These stations improve access to fast-growing villa communities and plotted developments nearby.
Airport Trumpet & Terminal:
These stations provide direct entry to airport terminals for passengers and airport employees.
Strategic Importance for Bangalore
The Suburban Rail Airport Corridor is not just a transport project. It is a long-term answer to Bangalore’s increasing mobility challenges. The line offers a reliable alternative to road-based airport travel, which often faces heavy traffic delays.
Reduced Travel Time:
Commuters can reach the airport from the city centre in about 45 min, independent of road congestion.
Cost-Effective Travel:
Fare prices are expected to be much lower than private cabs and app-based taxi services.
Integration with Metro:
The corridor is planned to integrate with the Namma Metro Blue Line, offering multiple public transit options to the airport.
Real Estate and Economic Impact
Progress on the Suburban Rail project has sparked strong growth in North Bangalore’s real estate market. Interested investors are investing in projects that are close to the upcoming metro stations because of smooth connectivity.
Commercial Growth:
Several IT companies and logistics firms are establishing offices near Devanahalli and the Aerospace Park.
Residential Demand:
Demand for apartments and premium villas in Hebbal and Yelahanka peaked in 2026.
Property Value Growth:
Areas that are within a 5 Km radius of Sampige Line stations have recorded a good and steady increase in the value of land.
Future Outlook and Completion
The project missed its deadline, which was set for 2025; the current progress shows that the initial trial run on the Sampige Line may start from late 2027 onwards. The state govt and K-RIDE are working together for the same.
Both the govt and K-RIDE are working closely to ensure that timely stock procurement takes place for the operations to start soon. This will happen after the track is completed.
Puravankara Limited Prelaunch Project is Purva Northern Lights.