Purva Northern Lights Phase 3 Project Schedule
Purva Northern Lights Phase 3 is a 6.30 acres premium township located in the KIADB Aerospace Park corridor on Bagalur Road. The project is RERA approved with the number PRM/KA/RERA/1251/309/PR/210907/004300. The official launch date is 15 March 2026. Construction will first start with digging the land and building a two-level basement. After that, the builder will construct 2 towers, and each tower will have 30 floors built with a strong RCC structure. After the structure is finished, vitrified floor tiles and branded bathroom fittings will be installed. At the same time, electrical wiring, plumbing, tower facades, and sewage treatment plants (STPs) will be built. The township will also have a large 1 lakh sq. ft. clubhouse and many lifestyle amenities. In the final stage, common areas like the vehicle-free central podium and landscaped gardens will be completed. The expected possession date is 31 December 2030.
Project Schedule & Key Milestones of Purva Northern Lights Phase 3
Building a tall township like Purva Northern Lights Phase 3 needs a clear and well-planned timeline so the work is done properly and on time. The construction will happen in different stages, starting from digging the land (excavation) and ending with the final work on the large 1 lakh sq. ft. clubhouse and other amenities. By following this step-by-step plan, the builder aims to complete the 2 towers and all facilities and give possession by 31 December 2030.
- Sub-Structure
The Sub-Structure stage is the first part of construction. It includes land preparation, foundation work, basement parking floors, and retaining walls that support the building from below ground level. This stage creates a strong base for the towers before the upper floors are built.
| Project Work | Estimated Start Date | Estimated End Date |
| Earth work and other levelling preparation work | 15 April 2027 | 30 September 2027 |
| Foundation footing work | 10 August 2027 | 30 March 2028 |
| Up to Plinth Level | 10 August 2027 | 30 March 2030 |
| Sub-structure flooring (Parking floor below ground level) | 10 January 2028 | 30 July 2028 |
| Retaining wall (All types) | 10 November 2027 | 30 November 2028 |
- Super-Structure
The Super-Structure stage is when the main building above the ground level is constructed. It includes building the RCC tower structure, walls, plastering, doors, windows, flooring, and basic utility systems like water, sanitation, and electricity. This stage forms the actual shape and living spaces of the towers.
| Project Work | Estimated Start Date | Estimated End Date |
| RCC or MS Framed Structure | 10 February 2028 | 30 March 2030 |
| Masonry Construction | 10 February 2028 | 30 March 2030 |
| Plastering inside, outside & ceiling | 10 July 2028 | 30 March 2031 |
| Joinery: Doors, Windows, Ventilators, etc. | 10 July 2028 | 30 March 2031 |
| Basic work of Water supply, Sanitary and Electrification | 05 April 2029 | 30 October 2031 |
| Dadoing, Skirting, Flooring, Tiles work (All types) | 07 November 2028 | 30 June 2031 |
| Railing and Grill Fixing | 10 June 2029 | 30 December 2030 |
- Finishing Works (Fitting and Fixtures)
The Finishing Works stage includes the final work done before the homes are ready to be lived in. It includes painting, electrical and water fittings, fire safety systems, and outside building design. This stage also completes important services and landscaping, so the project looks finished and ready for residents.
| Project Work | Estimated Start Date | Estimated End Date |
| Electrification, Water Supply and Sanitary Finishing | 10 July 2028 | 30 December 2030 |
| Painting | 07 May 2029 | 30 December 2031 |
| Fire Prevention and Fire Fighting Fittings with Network | 10 January 2029 | 30 May 2031 |
| Elevation Work | 10 June 2030 | 30 December 2031 |
| Internal and External Work | 10 December 2029 | 30 December 2031 |
- Internal Infrastructure
The Internal Infrastructure of Purva Northern Lights Phase 3 includes the basic systems that help the township work properly and keep people safe. These include water supply, sewage and drainage systems, rainwater harvesting, fire safety systems, waste management, and emergency evacuation services. These facilities help provide clean water, proper waste disposal, and safety for residents. The work for these systems is planned to happen from June 2028 to August 2030, so that all important services are ready before people move into their homes.
- External Infrastructure
The External Infrastructure phase includes the important outdoor works in the township. This phase includes building internal roads, footpaths, street lights, and electricity systems like substations and transformers. The project will also have trees in parks and a Sewage Treatment Plant (STP) to keep the area clean and green. All these outdoor works are planned to be finished by December 2030, so the community will be ready when people move in.
- Amenities
The amenities at Purva Northern Lights Phase 3 include many facilities for comfort, fun, and daily life. The project will have electricity and power backup (2983 sq m), a large clubhouse (8696 sq m), outdoor sports areas (3100 sq m), indoor sports areas (9696 sq m), a swimming pool (2874 sq m), a gym (8696 sq m), parks and green spaces (9032 sq m), and water and sanitation systems (4890 sq m). However, smart home automation, CCTV, piped gas, and central air conditioning are not included. These amenities are planned to be built between June 2028 and December 2031, so they are ready when people move in.
- Common Areas
The Common Areas in Purva Northern Lights Phase 3 are the shared spaces that everyone in the building can use. These areas help people move around the building easily and safely. The project will have staircases (9979 sq m), lifts (227 sq m), and corridors and lobbies (2852 sq m) that connect all the apartments. For safety, there will also be fire escape areas (65 sq m). Other shared spaces include a basement area (3067 sq m), a terrace (1249 sq m), and open parking areas (206 sq m). These shared spaces will be developed alongside the main buildings, with work finishing in time for the final project handover by 31 December 2030.